SCT DAQ Job List Following ID Week

12th October 2005

For SCT and Combined SCT/TRT running in SR1 December 2005 onwards

Aim: to have a suitable, tested, DAQ ready as the baseline to use by 18th November

1. Complete tests of DAQ migrated to SLC3 and tdaq-01-02-00, with modules, as the baseline system, to include all good features of release 4.2 (and more)

2. In parallel, study move to tdaq-01-04-00, with the aim of making this the version we use – Chris, John, Bruce

3. SctApi

4. DSP Code – Peter, Trevor?, Bruce

5. SctGUIDave

6. Move to private SR1 network – Dave

7. RodCrateDAQ?Chris

8. Multi Crate DAQ – Chris

9. Implementation of LTP

10. Monitoring in Athena – Luca? + Shaun

11. TIM and firmware – Alan and Matt

12. Specify and buy Processors for analysis for the pit – John

13. Readout through SLink

14. IS speed issue – Alan is testing existing implementation

15. Database