Available test systems
Short-term test systems
- Barrel5 - the afternoon and evening were spent testing the DAQ code on 24 modules on B5 (R4-updated). There is unlikely to be very much time for DAQ testing on B5 at SR1.
 - There may also be an opportunity to test the DAQ on Barrel4 at Oxford if the mounting and testing goes quickly.
 
BarrelSector
The BarrelSector? needs a refurbished cooling loop, harnesses, and a selection of modules, including those with known problems taken off other barrels
- This requires: 
- Harnesses to come from Taiwan and/or repaired.
 - Someone (from RAL?) to do the repairs to the services
 - Oxford to maintain the correct robot + cooling, and 24 module testing ability
 - Brackets, screws, clips etc.
 
 - Module mounting only to proceed after Barrel4 is completed
 - Host institution tbd.
 - Time-scale - target of end of August for fully populated sector
 
Janet Carter to coordinate this effort.
Spare Disk
- The endcap may encounter different problems, and so a separate endcap test system is desirable
 - NIKHEF should make a spare disk, but not until after 9-disks are assembled
 - time-scale - April 2006?
 
DAQ development effort
TDAQ
- Chris will arrange with Dave and CERN experts to go to CERN as soon as possible to sort out: 
- first the xml files for the new TDAQ release (-01-01)
 - then the RodCrateDaq? implications
 
 
Error Counting
- Alan to find out from Trevor what the pixel code does with errors
 - Peter and Alan to define what behaviour we actually want (dont re-send trigger?)
 - Alan to find out from Trevor timescale for implimenting changes
 
Redundancy
JohnHill? to:
- ensure that y-junction in the Barrel TX fibres follow the redundancy loops
 - find out if there are particular endcap modules which need to be run in select 1 and so would benefit from a particular ROD mapping
 
- Off-Rod redundancy 
- "Written but not tested" - says Bruce
 - Later in the day Bruce made some further changes to how this is handled in R4-updated at Oxford.
 - Alan is to merge this into HEAD (done), and to fix for sendABCDModule (singular) and modifyABCDVarROD (single module)
 - proper testing requires fix of SynchTrigs? (done)
 
 
- Off-crate rudundancy 
- Nothing exists yet.
 
 
Scan Options
- Alan to add missing scan options to analysis stream (done AJB)
 - A more flexible system of tests is eventually desirable (progress made, AJB)
 
Other requirements for cosmics running
- JohnHill? to work out if and what work needs to be done on the trigger chain.
 - Timing in. Full-mode histogramming needs to be tested - no name against this 
- BJG SctApi and DSP code should work (did as of Feb 04)
 - BJG Probably good idea to try and see what breaks
 - BJG Scan option to analysis stream would help things
 
 - Passive histogramming setup for passive histogramming needs to be checked. no name against this
 
Other
- Multi-crate - further development to be driven by user's debugging requests
 - Database issues were not discussed
 
- Dave to add pin current to GUI DCS display.