Available test systems
Short-term test systems
- Barrel5 - the afternoon and evening were spent testing the DAQ code on 24 modules on B5 (R4-updated). There is unlikely to be very much time for DAQ testing on B5 at SR1.
- There may also be an opportunity to test the DAQ on Barrel4 at Oxford if the mounting and testing goes quickly.
BarrelSector
The BarrelSector? needs a refurbished cooling loop, harnesses, and a selection of modules, including those with known problems taken off other barrels
- This requires:
- Harnesses to come from Taiwan and/or repaired.
- Someone (from RAL?) to do the repairs to the services
- Oxford to maintain the correct robot + cooling, and 24 module testing ability
- Brackets, screws, clips etc.
- Module mounting only to proceed after Barrel4 is completed
- Host institution tbd.
- Time-scale - target of end of August for fully populated sector
Janet Carter to coordinate this effort.
Spare Disk
- The endcap may encounter different problems, and so a separate endcap test system is desirable
- NIKHEF should make a spare disk, but not until after 9-disks are assembled
- time-scale - April 2006?
DAQ development effort
TDAQ
- Chris will arrange with Dave and CERN experts to go to CERN as soon as possible to sort out:
- first the xml files for the new TDAQ release (-01-01)
- then the RodCrateDaq? implications
Error Counting
- Alan to find out from Trevor what the pixel code does with errors
- Peter and Alan to define what behaviour we actually want (dont re-send trigger?)
- Alan to find out from Trevor timescale for implimenting changes
Redundancy
JohnHill? to:
- ensure that y-junction in the Barrel TX fibres follow the redundancy loops
- find out if there are particular endcap modules which need to be run in select 1 and so would benefit from a particular ROD mapping
- Off-Rod redundancy
- "Written but not tested" - says Bruce
- Later in the day Bruce made some further changes to how this is handled in R4-updated at Oxford.
- Alan is to merge this into HEAD (done), and to fix for sendABCDModule (singular) and modifyABCDVarROD (single module)
- proper testing requires fix of SynchTrigs? (done)
- Off-crate rudundancy
- Nothing exists yet.
Scan Options
- Alan to add missing scan options to analysis stream (done AJB)
- A more flexible system of tests is eventually desirable (progress made, AJB)
Other requirements for cosmics running
- JohnHill? to work out if and what work needs to be done on the trigger chain.
- Timing in. Full-mode histogramming needs to be tested - no name against this
- BJG SctApi and DSP code should work (did as of Feb 04)
- BJG Probably good idea to try and see what breaks
- BJG Scan option to analysis stream would help things
- Passive histogramming setup for passive histogramming needs to be checked. no name against this
Other
- Multi-crate - further development to be driven by user's debugging requests
- Database issues were not discussed
- Dave to add pin current to GUI DCS display.